Final report for construction works
A final report is prepared by the contract administrator at the end at the end of the defects liability period once all defects have been rectified.
The final report should provide a summary of activities during the construction phase, describing:
- The works that have been completed.
- The variations that have been agreed.
- Claims for loss and expense or extension of time that have been agreed.
- The original contract sum.
- The final account.
- The completion date.
It is useful if both parties to the contract sign off the financial aspects of the report as representing the full and final settlement for the contract.
It can also be useful to prepare an end of contract report that provides greater detail about the performance of the contractor and is a record that can be referred to in the future in the event of public scrutiny, legal proceedings or if a judgement is being made about whether to employ the contractor again. See end of contract report for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.